Hi, Is there a way to change/control the primary node (i.e. where the initial task starts) as part of a job's allocation. For eg, if a job requires 6 CPUs & its allocation is distributed over 3 hosts h1, h2 & h3 I find that it always starts the task in 1 particularnode (say h1) irrespective of how many slots were available in the hosts. Can we somehow let slurm have the primary node as h2? Is there any C-API inside select plugin which can do this trick if we were to control it through the configured select plugin? Thanks.-Bhaskar.
Likely many ways to do this, but if you have some code that is dependent on something, that check could be in the code itself.
So instead of process 0 being the required process to run, it would be whichever process meets the requirements.
eg:
case hostname: harold) Run harold's stuff here *) Run all other stuff here esac
Takes some coding effort but keeps control of the processes within your own code.
Brian Andrus
On 10/30/24 09:35, Bhaskar Chakraborty via slurm-users wrote:
Hi,
Is there a way to change/control the primary node (i.e. where the initial task starts) as part of a job's allocation.
For eg, if a job requires 6 CPUs & its allocation is distributed over 3 hosts h1, h2 & h3 I find that it always starts the task in 1 particular node (say h1) irrespective of how many slots were available in the hosts.
Can we somehow let slurm have the primary node as h2?
Is there any C-API inside select plugin which can do this trick if we were to control it through the configured select plugin?
Thanks. -Bhaskar.
Hi Brian,Thanks for the response!However, this particular approach where we need to accept whatever slurm gives us as starting nodeand deal with it accordingly doesn’t work for us. I think there should be flexibility in slurm to switch the starting node as requested,through some C API. This is possible in other scheduling system like LSF. Any other way to do this with the current slurm code base is welcome. Regards,Bhaskar.
Sent from Yahoo Mail for iPad
On Friday, November 1, 2024, 1:12 AM, Brian Andrus via slurm-users slurm-users@lists.schedmd.com wrote:
Likely many ways to do this, but if you have some code that is dependent on something, that check could be in the code itself.
So instead of process 0 being the required process to run, it would be whichever process meets the requirements.
eg:
case hostname: harold) Run harold's stuff here *) Run all other stuff here esac
Takes some coding effort but keeps control of the processes within your own code.
Brian Andrus
On 10/30/24 09:35, Bhaskar Chakraborty via slurm-users wrote:
Hi, Is there a way to change/control the primary node (i.e. where the initial task starts) as part of a job's allocation. For eg, if a job requires 6 CPUs & its allocation is distributed over 3 hosts h1, h2 & h3 I find that it always starts the task in 1 particular node (say h1) irrespective of how many slots were available in the hosts. Can we somehow let slurm have the primary node as h2? Is there any C-API inside select plugin which can do this trick if we were to control it through the configured select plugin? Thanks. -Bhaskar.
Bhaskar,
As I think about it, that assignment of process 0's node may well be something that is from your mpi, since that is where you can decide how to layout the processes (pack a node or equally, etc). I would look at the options/settings that apply to the particular flavor of mpi you are using.
For example, in openmpi, it has:
To order processes' ranks in MPI_COMM_WORLD:
--rank-by <foo> Rank in round-robin fashion according to the specified object, defaults to slot. Supported options include slot, hwthread, core, L1cache, L2cache, L3cache, socket, numa, board, and node.
Brian Andrus
On 11/3/2024 12:06 AM, Bhaskar Chakraborty wrote:
Hi Brian, Thanks for the response! However, this particular approach where we need to accept whatever slurm gives us as starting node and deal with it accordingly doesn’t work for us.
I think there should be flexibility in slurm to switch the starting node as requested, through some C API. This is possible in other scheduling system like LSF.
Any other way to do this with the current slurm code base is welcome.
Regards, Bhaskar.
Sent from Yahoo Mail for iPad https://mail.onelink.me/107872968?pid=nativeplacement&c=Global_Acquisition_YMktg_315_Internal_EmailSignature&af_sub1=Acquisition&af_sub2=Global_YMktg&af_sub3=&af_sub4=100000604&af_sub5=EmailSignature__Static_
On Friday, November 1, 2024, 1:12 AM, Brian Andrus via slurm-users slurm-users@lists.schedmd.com wrote:
Likely many ways to do this, but if you have some code that is dependent on something, that check could be in the code itself. So instead of process 0 being the required process to run, it would be whichever process meets the requirements. eg: case hostname: harold) Run harold's stuff here *) Run all other stuff here esac Takes some coding effort but keeps control of the processes within your own code. Brian Andrus On 10/30/24 09:35, Bhaskar Chakraborty via slurm-users wrote: Hi, Is there a way to change/control the primary node (i.e. where the initial task starts) as part of a job's allocation. For eg, if a job requires 6 CPUs & its allocation is distributed over 3 hosts h1, h2 & h3 I find that it always starts the task in 1 particular node (say h1) irrespective of how many slots were available in the hosts. Can we somehow let slurm have the primary node as h2? Is there any C-API inside select plugin which can do this trick if we were to control it through the configured select plugin? Thanks. -Bhaskar. -- slurm-users mailing list -- slurm-users@lists.schedmd.com To unsubscribe send an email to slurm-users-leave@lists.schedmd.com
Hi Brian, We don't use MPI. Our use model initially launches a primary task (& a few lightweight child tasks) in the primary launch host.Thereafter, the primary task remotely launches parallel tasks in other allocated nodes through rsh/ssh or (preferably) a slurm equivalent app for remote task launch.(for eg., in LSF it's blaunch). We need a slurm equivalent remote task launch app as well, we don't know if there is any one yet. It's imperative that our primary task launches in the primary launch host as it needs to talk to the h/w beneath before going forward with other remote launches. -Bhaskar. On Monday 4 November, 2024 at 06:44:44 am IST, Brian Andrus via slurm-users slurm-users@lists.schedmd.com wrote:
Bhaskar,
As I think about it, that assignment of process 0's node may well be something that is from your mpi, since that is where you can decide how to layout the processes (pack a node or equally, etc). I would look at the options/settings that apply to the particular flavor of mpi you are using.
For example, in openmpi, it has:
To order processes' ranks in MPI_COMM_WORLD:
--rank-by <foo> Rank in round-robin fashion according to the specified object, defaults to slot. Supported options include slot, hwthread, core, L1cache, L2cache, L3cache, socket, numa, board, and node.
Brian Andrus
On 11/3/2024 12:06 AM, Bhaskar Chakraborty wrote:
Hi Brian, Thanks for the response! However, this particular approach where we need to accept whatever slurm gives us as starting node and deal with it accordingly doesn’t work for us. I think there should be flexibility in slurm to switch the starting node as requested, through some C API. This is possible in other scheduling system like LSF. Any other way to do this with the current slurm code base is welcome. Regards, Bhaskar.
Sent from Yahoo Mail for iPad
On Friday, November 1, 2024, 1:12 AM, Brian Andrus via slurm-users slurm-users@lists.schedmd.com wrote:
Likely many ways to do this, but if you have some code that is dependent on something, that check could be in the code itself.
So instead of process 0 being the required process to run, it would be whichever process meets the requirements.
eg:
case hostname: harold) Run harold's stuff here *) Run all other stuff here esac
Takes some coding effort but keeps control of the processes within your own code.
Brian Andrus
On 10/30/24 09:35, Bhaskar Chakraborty via slurm-users wrote:
Hi, Is there a way to change/control the primary node (i.e. where the initial task starts) as part of a job's allocation. For eg, if a job requires 6 CPUs & its allocation is distributed over 3 hosts h1, h2 & h3 I find that it always starts the task in 1 particular node (say h1) irrespective of how many slots were available in the hosts. Can we somehow let slurm have the primary node as h2? Is there any C-API inside select plugin which can do this trick if we were to control it through the configured select plugin? Thanks. -Bhaskar.