[slurm-users] How to get an estimate of job completion for planned maintenance?
    Chris Samuel 
    chris at csamuel.org
       
    Wed Nov 10 02:29:53 UTC 2021
    
    
  
On 9/11/21 5:42 am, Loris Bennett wrote:
> We just set up a reservation at a point at a time which is further in the
> future than our maximum run-time.  There is then no need to drain
> anything.  Short running jobs can still run right up to the reservation.
This is the same technique we use too, works well!
All the best,
Chris
-- 
  Chris Samuel  :  http://www.csamuel.org/  :  Berkeley, CA, USA
    
    