[slurm-users] "allocated+" status

Andy Riebs andy.riebs at hpe.com
Mon Apr 16 09:43:26 MDT 2018


I hadn't realized that jobs can be scheduled to run on a node that is 
still in "completing" state from an earlier job. We occasionally use 
epilog scripts that can take 30 seconds or longer, and we really don't 
want the next job to start until the epilog scripts have completed.

Other than coding a little loop to wait until the desired nodes are 
"idle" before scheduling a job, is there an automated way to say "don't 
start a job on a node until it reaches 'idle' status?"

Andy

-- 
Andy Riebs
andy.riebs at hpe.com
Hewlett-Packard Enterprise
High Performance Computing Software Engineering
+1 404 648 9024
My opinions are not necessarily those of HPE
     May the source be with you!




More information about the slurm-users mailing list